The following is a newsletter from Bugler, the developers of KewSide (Autobar House):

Dear Residents,

Friday 6th
We may be late with today’s pour due to a break in last night all of the surveying equipment was stolen, this has coursed a delay in the pour times due to waiting for the replacements so the decking could be levelled.  We will do our best to be completed on time.

I would like to ask did anyone see anything on Thursday night / Friday morning?

Programmed Works for week ending 15th February 15

Monday 9th
1 load of Re-bar am

Tuesday 10th
1 load of Scaffolding.

Wednesday 11th
6+ loads concrete am, 1 load of steel.

Thursday 12th
1 load of precast columns,  1 load of blocks

Friday 13th
6+ loads of concrete,

Saturday & Sunday
Not Working.

Please Note:- Scaffolding to the Riverside Block has been programmed in to start W/C 9th February 15, This will involve scaffolding over 57 & 58 Regatta Point & removing the hoarding along the footpath on the Thames Row boundary.

These deliveries programmed above may change due to unforeseen circumstances.

Sorry for any inconvenience

Martyn Brooks – Project Manager