OUTSTANDING ACTIONS
LOBBY POWER:
Workmen now in site clearing out and repairing electrical cupboard. Need to strip out debris and repair. This will re-connect caretaker’s office, lobby, gym, stairwell C to power supply – expected to complete by Friday 6th February.
FIRE BRIGADE REPORT:
Inspections completed and awaiting report – no planned date as yet.
GENERAL CLEANING:
Awaiting confirmation from the insurers as to when their insurers will attend to clean the carpets and deodorise the building. Initial indication is mid next week.
CAR PARK DAMAGE:
Caused by the need to get at power cables – SSE have relaid cables and contractors filled in hole. New tarmac required – expected to be completed by Thursday the 29th of January.
SECURITY:
Front door lock out of action overnight security guards in place but obsolete fittings may require new unit to be fitted – no planned date as yet.
You may be challenged as to who you are by overnight security.
ENTRYPHONE:
HML await quotes for the temporary and full reinstatement of the system although these are both reliant on an electrical supply. It will be reconnected as soon as possible – no planned date as yet.
BLOCK C TELEPHONE LINES:
Supplied by BT, they have inspected site and await electrical room remedial work to be completed before starting work – no planned date as yet.
BLOCK C VIRGIN MEDIA CABLE:
Have been informed but no site visit as yet – no planned date as yet.
In the meantime – don’t forget that modern flat-screen TVs can be attached to the standard TV aerial socket and tuned in to Freeview.
BLOCK C LIFT:
Needs full inspection after power re-supply – as soon as HML have a reconnection day for the communal electrics they will ask Arrow Lifts to attend. No planned date as yet.
COMPLETED ACTIONS
INSURANCE:
Loss adjust has completed visit and all costs/actions are being agreed with insurer as we progress works.