moulinLadies & Gentlemen, you are cordially invited to the Summer BBQ to be hosted on the pier from 6pm on Saturday July the 26th.  This year’s theme is Moulin Rouge and we hope that you will join in the competitions for the best Moulin Rouge style pudding or the best Moulin Rouge style costume.  We expect competition to be fierce and fun!

As per usual, the Social Committee will be working hard to provide you with the BBQs, plates, cutlery, glasses, napkins, soft drinks and a welcoming glass of wine.  All you have you do is bring your own food and all the latest gossip.

Please take this opportunity to re-acquaint yourselves with long lost neighbours or meet them for the first time.  The event is free and open to residents, ex-residents, friends and family.  Please sign-up on the notices placed around the buildings so that we can cater for the correct amount of guests.

The Regatta Point Social Committee

St George’s liaison meeting – May 2014

The following are minutes from the regular meeting between St George’s and RPFL.

MINUTES FROM MEETING BETWEEN REGATTA POINT &  ST GEORGE’S ON 16TH MAY 2014

ATTENDEES:
George Cross (Regatta Point Freehold Limited Director), Sean Chappell (St. George’s Project Director) and Malcolm Wood (St. George’s Land Director).

APOLOGISES:
Mo Bowyer (Regatta Point Resident),

MINUTES: (StG = St George’s RP= Regatta Point)

Work progressing well. Excavation for C1 imminent. Pile driving will be necessary to form protective wall around perimeter. Should not cause too much disturbance.

Block D (next to Regatta) & E – party wall agreement imminent as all work to explore ground has been completed. A lot of unexpected services were found and the local utility companies have been re-laying gas and electric.

StG assured that the next phase will be sprayed properly when required but soil is expected to be damp as below the water table. Regatta Point will be in contact if we require action over the dust levels.

Major issue of co-ordination of StG building work on block D and RP requirement to carry out works to strengthen Eastern wall. StG have determined the floor levels of each building and it will be possible to get contractors on site at StG as each floor is built in order to carry out Helifix remedial works to Regatta Point Eastern Wall. RP expressed their gratitude.

StG offered potential suppliers for RP roadside window tender.

StG have been in discussions with Hounslow Council over the implementation of gates at either end of RP/StG boarder. The council have agreed to the proposal.

Entire duration of development expected to last in to 2016.

Next meeting for Friday 13th June at 08:30

Just a reminder…

Dear Resident,

The Regatta Point Social Committee would like to invite any residents who fancy a drink with their neighbours to join us at just before 9pm on the evening of Thursday the 29th of May as we will be gathering in the lobby to them walk over the bridge to the Cricketers pub in order to have an informal get together.

All are welcome and we’d love to see you there.

The Regatta Point Social Committee

social

social

Autobar House Development Update

The following are notes on the regular liaison meeting between Regatta Point, Thames Row and Bulger Development.

Meeting 22 May 2014
In Attendance Mark Varley & Martyn Brooks (Bugler), Stephanie Henderson-Brown (RPFL Director), David Nightingale & Julia Chen (Regatta Point)
Mark Fullalove & Sue Carter (Thames Row), James & Louise Muggoch (Chilham) and Leonora Saunders (Ciconia)

PROGRAMME TIMETABLE:

  • Current Programme Delay 15 weeks MV advises this has cost in excess of £100k thus far
  • Archaeology Ongoing Finds are very significant/ongoing watching brief from English Heritage
  • Asbestos Removal/Soft Strip – All but completed
  • Demolition start 22-May 6-8 weeks End 10-Jul Water suppression techniques will be employed to reduce dust
  • Scaffolding Demolition Phase Start 15-May 6-8 weeks End 10-Jul Scaffolding struck (removed) after demolition, until construction starts
  • Augered Piles Regatta Point Start end of June 4-5 days. Advance notice of this work will be provided closer to time
  • Viewable Site & Building Plans End 10-Jul Should be on site to coincide with next meeting/No scale model
  • Construction Phase TBC
  • Long Stop Date End Jun-15
  • Bricklayers on site Jan-15 Depends on progress/For rebuilding of RP boundary wall
  • Site Offices Start 19-May  end Jun-15
  • Completion Roadside Building Jul-15 has priority on occupation, but built at the same time
  • Completion Riverside Building Oct-15
  • Bugler Contract Completion Date Nov-15

Party Wall:
Most issues resolved on Thames Row side/awards should be granted soon/should not hold up works
JC & DN advised by MV to contact PW Surveyor Peter Messenger directly re concerns: SHB to provide contact details
Scaffolding Detail:
Regatta Mews licence pending/Regatta Point Access Licence Agreed / Thames Row licence agreed and assumed signed
Thames Row Boundary Wall:
The wall will be reduced to 2340mm
If not structurally sound, will be reduced to repair and then be rebuilt to the agreed height
Flank wall of building will be reduced to same level: stepping down to accommodate slope
Will be approximately 2800mm at Thames side (level of existing metal grilles)
Thames Row Access Visibility:
SC raised issue of problem with turning right out of Thames Row, since site offices installed
MV agreed that a domed mirror would be installed on the pole in the centre junction, to aid visibility
Regatta Point Car Park:
Car park space & loggia to be reinstated after works completed: boundary will always be secure
Car park spaces under scaffold may be used as normal (notice will be given if this changes)
Regatta Point Piling:
35 x Augered piles will be 16 metres deep, at 1.2m centres from RP wall
Regatta Point Mural:
Undertaking exists to keep at least 1 metre of mural: MV advises that significantly more than this may remain
Houseboat Electrical Install:
Cabling has been made fit for future usage
Cabling will remain on private land side, until it is installed underground, programme dependent