The following is a newsletter from Bugler, the developers of KewSide (Autobar House):
Dear Residents,
Programmed Works for week ending 8th February 15
Monday 2nd
9+ loads of concrete am start.
Tuesday 3rd
1 load of Precast columns delivery 10am.
Wednesday 4th
1 load of Re-bar delivery am.
Thursday 5th
1 load of Precast columns 10am & 1 load of Re-bar pm.
Friday 6th
4+ loads of concrete 12pm, 1 load of precast columns & 1 load of scaffolding.
Saturday & Sunday
Not Working.
Please Note:- Scaffolding to the Riverside Block has been programmed in to start on 9th February 15, This will involve scaffolding over 57 & 58 Regatta Point & removing the hoarding along the footpath on the Thames Row boundary. There will also be two loads of bricks, date & times TBC.
These deliveries programmed above may change due to unforeseen circumstances. Sorry for any inconvenience
Martyn Brooks – Project manager