OUTSTANDING ACTIONS
LOBBY POWER:
Need to strip out debris and repair. This will re-connect caretaker’s office, lobby, gym, stairwell C to power supply.
A few problems have been encountered with the lift supply (which has been prioritised) and tracing a fault in the gym/lighting circuits. We currently await confirmation as to when the lift supply will be in place so we can get the lift engineers in to test and get running. Maber are schedule to have their “fire stopping” contractors on site to carry out the necessary repairs in the riser cupboard. Most work should be completed by Friday.
GENERAL CLEANING:
As you will have seen and smelt the common parts have now been deodorised and do seem to be smelling better, this also involved the carpet being cleaned at 1st floor level for the length of the building and staircase in block c. They have also cleaned the gym. We are aware of some areas that still do with an additional clean and will follow this up with the contractor.
BLOCK C TELEPHONE LINES:
BT have attended and identified exactly what works they wish to undertake. Work will be co-ordinated with Maber in regard to getting into the cupboard once they have finished the electrical works.
BLOCK C VIRGIN MEDIA CABLE:
Virgin have escalated the repair to a senior manager as it may be a significant repair job – we wait to hear when they are able to attend to reinstall the necessary cabling.
In the meantime – don’t forget that modern flat-screen TVs can be attached to the standard TV aerial socket and tuned in to Freeview.
BLOCK C LIFT (no change):
Needs full inspection after power re-supply – as soon as HML have a reconnection day for the communal electrics they will ask Arrow Lifts to attend. No planned date as yet.
SECURITY (no change):
Front door lock out of action overnight security guards in place but obsolete fittings may require new unit to be fitted – no planned date as yet.
You may be challenged as to who you are by overnight security.
ENTRYPHONE (no change):
HML await quotes for the temporary and full reinstatement of the system although these are both reliant on an electrical supply. It will be reconnected as soon as possible – no planned
date as yet.
FIRE BRIGADE REPORT (no change):
Inspections completed and awaiting report – no planned date as yet.
COMPLETED ACTIONS
CAR PARK DAMAGE:
repairs to tarmac in car park have been completed.