Category Archives: Local redevelopment

KewSide/Bugler liaison meeting

The next liaison meeting between Regatta Point and Bugler (the Kewside developers) has been arranged for 1pm on Monday the 8th of June – any resident wishing to attend should rendezvous in the site office which is accessed by entering the site and climbing the stairs.

You should be directed to the office by the workmen on the gate.  Inform them you are attending a meeting with Mark Varley.

Please let the director know you are attending by emailing steph@henderson-brown.com

St George’s liaison meeting

On Friday the 6th of March George Cross (RP Director), Mo Bowyer (RP resident),Malcolm Wood (St. George’s) ,  and Sean Chappell (St. George’s Snr. Construction Manager) held one of their regular liaison meetings – the aim of which is for Regatta Point to raise any issues with the development next door and for St George’s to keep us abreast with progress.

The following are highlights of the meeting:

COORDINATION OF ST.G WORK AND HELIFIX WORK TO RP EAST WALL
All floors are expected to be available for RP contractors to carry out Helifix remedial works from the end of March.  The work is expected to take up to 2 weeks, will be during normal working hours of 8am to 6pm and be very noisy.
GENERAL PROGRESS

  • The last concrete will be poured by the end of March, completing the superstructure of the building.
  • The next phase of the building around Providence House will have its public spaces opened up, both front and back, by April.
  • The crane is scheduled to be removed in July.  This will require weekend working and likely temporary road closure.
  • Scaffold and then protective wrapper has started to go up around the oval and connecting building as work commences on the internal fit-out.  Work will continue in this area (which excludes the roadside block that abuts Regatta Point) until the end of November 2015, after which the area will be opened to the public – including access to the side gate for boat owners.
  • The tall, overgrown, trees and bushes next to RP wall are to be removed and replaced by low level shrubs.  Security is to be maintained by the implementation of gates at the roadside and riverside end of the development that will be locked overnight with key codes issued to St George’s residents and some boat owners.
  • The completion of the rest of the roadside site is expected to be spring/summer 2016.
  • No more commercial units have been let.

Next meeting Friday 5th June 08:30am.

Bugler/KewSide Newsletter – Friday 6th February

The following is a newsletter from Bugler, the developers of KewSide (Autobar House):

Dear Residents,

Friday 6th
We may be late with today’s pour due to a break in last night all of the surveying equipment was stolen, this has coursed a delay in the pour times due to waiting for the replacements so the decking could be levelled.  We will do our best to be completed on time.

I would like to ask did anyone see anything on Thursday night / Friday morning?

Programmed Works for week ending 15th February 15

Monday 9th
1 load of Re-bar am

Tuesday 10th
1 load of Scaffolding.

Wednesday 11th
6+ loads concrete am, 1 load of steel.

Thursday 12th
1 load of precast columns,  1 load of blocks

Friday 13th
6+ loads of concrete,

Saturday & Sunday
Not Working.

Please Note:- Scaffolding to the Riverside Block has been programmed in to start W/C 9th February 15, This will involve scaffolding over 57 & 58 Regatta Point & removing the hoarding along the footpath on the Thames Row boundary.

These deliveries programmed above may change due to unforeseen circumstances.

Sorry for any inconvenience

Martyn Brooks – Project Manager

Complaints regarding Bugler.

Many residents are suffering from the poor working practices of Bugler (the developers of KewSide/Autobar).

So as to raise the profile of the problems and in order to get a change of behaviour could any resident impacted please complain to any or all of the following:

1. Considerate Contractors Scheme:
http://www.ccscheme.org.uk/index.php/affected-by-works/complaints-procedure

2. Make a noise complaint to Hounslow
http://www.hounslow.gov.uk/noise_nuisance_reporting

3. Complaint to Planning Enforcement regarding breach of agreed Logistics Plan
http://www.hounslow.gov.uk/index/environment_and_planning/planning/planning_enforcement.htm

St George’s Liaison Meeting – January 2015

On Friday the 30th of January Mo Bowyer (RP resident), and Sean Chappell (St. George’s Snr. Construction Manager) held one of their regular liaison meetings – the aim of which is for Regatta Point to raise any issues with the development next door and for St George’s to keep us abreast with progress.

The following are highlights of the meeting:

COORDINATION OF ST.G WORK AND HELIFIX WORK TO RP EAST WALL
SC said they would be ready for us to do this work the third week in March – contractor and weather dependent. Would like it to be completed in 1 week but 2nd week is OK.

SITING OF GATES INTO ST.G DEVELOPMENT
There will be a total of 4 gates, with 3 of them locked from dawn to dusk – set time would be agreed at a later date. There will be a locked gate at both the North and South ends of the pathway plus a 3rd, adjacent to which will be a 4th gate for residents operated by a fob.

HOARDING OBSTRUCTING VIEW WHEN LEAVING RP CAR PARK
SC appreciated the problem but said it was necessary as a safety measure as items could possibly fall from scaffolding during construction and is designed to contain any such debris. He hoped to have these hoardings removed by the end of August or earlier if possible. Small entrance to remain open but main entrance is being widened for main deliveries – bricks, etc.

GENERAL PROGRESS
SC said they will be working from the Elipse upwards and the work on the construction abutting RP will be the last. All frames should be in place by end of March. The crane will remain until the end of July.

When work begins next to RP in September time – scaffolding will be encased in white sheeting to minimise dust fall out, etc. Landscaping will follow.

All windows will be installed before the brickwork and there will obviously be increased noise from drilling/building activity.

The footpath wall should be finished in 6/8 weeks.

First handover of landscaped area in front of Provenance House should be at the end of this week, i.e. 6th February.

In discussion with 3 potential lettings for the retail/office spaces.

The completion of the site has been moved from Dec 2015 to spring/summer 2016.

 Next meeting Friday 6th March.