On Wednesday the 23rd of April the Directors of Regatta Point Freehold Limited met in order to review the report, compiled by our surveyors, regarding the responses to our tender document for the re-decoration of the internals of Regatta Point.
It was decided that the works will include the redecoration of all common areas of the building, new windows in the gym, sauna refurbishment and redecoration of the guest rooms and caretaker’s office.
Residents will soon receive a letter informing them of the decision and inviting comment.
The work is expected to take 6 weeks to arrange and 15 weeks to complete.
This is the last stage in the general overhaul of the building, both externally and internally, that will upgrade Regatta Point so as to improve our living environment and protect the value of our properties. The cost of these works will be covered by our sinking fund.