The following are the minutes from the regular liaison meeting between St George’s, Regatta Point Directors and Residents Representative which took place on Friday the 13th of June at 08:30.
ATTENDEES:
George Cross (Regatta Point Freehold Limited Director), Mo Bowyer (Regatta Point Resident), Sean Chappell (St. George’s Project Director) and Malcolm Wood (St. George’s Land Director).
APOLOGIES:
None
MINUTES: (StG = St George’s RP= Regatta Point)
Piling work on final construction two thirds complete. Method is proving to be very quiet..
There has been a delay in construction caused by the need to re-route the gas services away from the pipe running alongside RP. The utility company has been slow in responding but they are now progressing the work.
The party wall agreement will be with the RP surveyor inspection and for sign-off next week. However, the piling rig is not available until July the 7th so that is the earliest date for the next phase to start. In the meantime excavation will continue. There will be some sporadic drilling in order to break up any structures or concrete found.
The Eastern wall has red paint on it because they indicate points on the wall where measurements have been taken and these points will be monitored on a regular basis to look out for any movement in the structure. Work would stop immediately if any movement was detected.
The final excavation is planned to be completed by the end of August.
All remaining buildings will then be built up to ground level (i.e. basements built). This is expected to be by October.
Construction of the concrete super structure for all buildings will then start – alternating from building to building as concrete is poured and sets. Concrete frame expected to be complete by end Jan 2015. The crane will then be dismantled.
Pub will be handed over to Fullers by the first of July for an 8 week fit-out.
Entire duration of development expected to last up to 2016.
Next meeting for Friday 12th September at 08:30
Very much appreciate the time and effort to keep us all informed.
Any news when they remove the plants/ greenery adjacent to side path & Regatta?
Thanks again